Don't Overlook Control Joints in Drywall Construction
By George M. Kutcher, Jr., CDT, CSI
One component of gypsum board construction often overlooked by architects and contractors
is the control joint. Architects sometimes fail to specify control joints. In some
cases when control joints are specified, the drawings are not coordinated with the
specifications and the control joint details are frequently missed. Even in the
best of circumstances, when control joints have been specified and properly detailed,
estimators may neglect to include them in the bid and project managers are faced
with managing a job with unforeseen costs.
Gypsum wallboard, as well as other building products and materials, is subject to
some form of movement induced by changes in moisture, temperature or both. To relieve
the stresses that occur as a result of such movement, control joints are required
in both partitions and ceilings.
Control joints are frequently necessary to prevent cracking in gypsum wallboard.
Cracking may also be caused by stresses resulting from building movement. Isolation
joints should be installed where structural elements such as slabs, columns or exterior
walls can bear directly on non-load bearing partitions.
Control joints should be employed in long expanses of partitions at 30-foot intervals,
from floor to ceiling. Control joints are recommended at doorjambs, extending from
door head to ceiling. Where doorjambs extend from floor to ceiling and are spaced
less than 30 feet apart, no control joints are required.
When "through wall" control joints are required in fire-rated assemblies, special
details (See drawing) are necessary. These details
are based on Warnock Hersey International, Inc. Report WHI 651-0318.1.
Control joints are required in ceilings to limit areas to 2,500 square feet. Additionally,
control joints should be installed in ceilings to limit dimensions in either direction
to 50 feet. Control joints should be installed where ceiling framing or furring
changes direction.
Even if control joints do not appear to be specified they are often covered by reference
specification. Carefully read PART 1, GENERAL, Paragraph 1.02 REFERENCES, of the
Gypsum Board specifications. More than likely, the architect has referenced either
ASTM C 840, The Standard Specification for Application and Finishing of Gypsum Board;
GA-216, the Gypsum Association Recommended Specification for Application and Finishing
of Gypsum Board; or both. The requirement for control joints is addressed in both
of these documents.
>