Installation and Usage Information
What thickness of PermaBase® should
I use for my project?
For residential walls and ceilings you should use 1/2" or 5/8" PermaBase; for floors
and countertops you can use either 1/4" or 1/2" depending on your subfloor and the
thickness of adjoining materials (such as the transition from tile to hardwoods).
If your subfloor is at least 3/4" thick then you can use 1/4" PermaBase; otherwise
you will need to use 1/2" PermaBase. 5/8” PermaBase is also produced for many commercial
applications.
>
Back to Top
Why is PermaBase available in different thicknesses? Or why is PermaBase
available as a 1/4" and a 1/2" thick panel?
In flooring applications it is important to match heights where there is a transition
from one floor covering product to another. PermaBase offers 1/4" and 1/2" material
for floor applications to ensure flexibility and a better transition from area to
area. 1/4" PermaBase also works well for countertops to help maintain a minimal
height impact when adding tile to an existing countertop.
>
Back to Top
Where can I use PermaBase?
Traditional cement boards like PermaBase are extremely versatile and can be used
in a variety of applications. PermaBase is perfect for interior uses such as floors,
walls, countertops, or ceilings. It is also a terrific product for exterior walls
and soffits for tile or stucco finishes. It is also an approved and frequently used
product for sauna’s and steam rooms.
>
Back to Top
How do I cut PermaBase?
It’s a simple process using a straight edge, pencil, and utility knife. Once you
have marked your cut, use the straight edge as a guide to firmly score the top mesh
of the board (noted by the printing that reads, “Cut this side”). Snap the board
downward and then use the utility knife to cut the back mesh leaving you with a
clean straight cut. As with all cutting operations it is recommended that you wear
eye protection such as safety glasses or goggles.
>
Back to Top
Which side should I use? Or should I tile a particular side of the
board?
PermaBase products have a tapered edge on one face so that once installed and taped
you have a level, uniform surface to adhere to with your finish treatment. Look
at both sides and you will see printing on the board on one which, which is the
side with the tapered edge. Install the printing side “out” so once installed you
should be able to read the printing. If you find that you have installed PermaBase
with the wrong side visible don’t worry, tile and stucco adhere equally well to
both sides of the panel.
>
Back to Top
What type of fasteners should I use - nails or screws?
You can use either nails or screws to fasten PermaBase to your floors, walls, ceilings,
or countertops. However, you will need to use either 1 1/2" hot-dipped galvanized
nails (roofing nails) or 1 1/4" PermaBase coated cement board screws. If you are
attaching PermaBase to 20 gauge or heavier metal framing, use 1 5/8" PermaBase cement
board screws. Drywall nails and screws should not be used as they are not alkali
resistant.
>
Back to Top
How often do I fasten the screws or roofing nails to secure the PermaBase?
On walls and floors/countertops, attach fasteners 8" o.c. in each direction. On
ceilings, attach fasteners 6" o.c. in each direction.
>
Back to Top
I have to make a hole or "cutout" for my pipes. How do I do that?
Place the PermaBase board on a solid support surface. Mark the location on the PermaBase
board to the size of the hole that is needed on the same side as the writing. Always
cut the side with printing. Using a utility knife, score the cutout. Using a regular
hammer, hit around the inside edges of the cutout. Tilt the board to allow the core
material to fall from the hole and then cut out the remaining back mesh. A router
and concrete bit may be used with a proper dust mask and, as always, eye protection.
>
Back to Top
Why do I have to trowel out a setting bed or support bed before placing
PermaBase on the floor?
The purpose of troweling out a 1/4" mortar bed or “support bed” is to provide a
leveling agent for the plywood subfloor. Differences in height between pieces of
plywood, whether it is from poor nailing, minor warping, floor joists, will affect
the tile if not addressed. The best way to ensure a solid base for your tile application
is to start with a plywood subfloor that does not exceed a 1/4" of variance for
every 10’ and to apply a 1/4" notched trowel bed of mortar in which the PermaBase
is then set and then nailed or screwed.
>
Back to Top
How much of a gap do I leave between boards?
When using PermaBase in a flooring or countertop application, boards should be spaced
1/8" apart. The gap will be filled by the mortar and alkali resistant tape to create
a solid uniform tile substrate. Also remember to leave a 1/4" gap around the perimeter
of the room to allow for subfloor movement.
>
Back to Top
Why do I have to tape and finish the seams?
Taping and finishing the seams with a thinset or mortar and an alkali resistant
mesh tape creates a uniform surface for your tile. It also helps prevent cracking
in the tile due to subfloor movement such as thermal expansion and contraction.
>
Back to Top
Do I need a vapor barrier behind PermaBase?
PermaBase is not a vapor barrier and an additional barrier is not required in most
conditions. In areas such as indoor pools and saunas, a vapor barrier is recommended.
>
Back to Top
Can I use 1/4" material on walls and ceilings as it is lighter to
handle?
1/4" PermaBase is only for floors and countertops where there is proper support
for the board. A minimum thickness of 1/2" should be used for walls and ceilings.
<
>
Back to Top
What if I have a curved application? Does PermaBase Bend?
Our standard 1/2" PermaBase product will bend to a 90° radius at 5’ and for tighter
radii you can use PermaBase Flex. PermaBase Flex is a specialty board specifically
made for curved applications. It is a 1/2" cement board that bends to 90° at a 6"
radius. This is done without having to wet or score the material prior to bending
it.
>
Back to Top
What type of warranty does National Gypsum offer on PermaBase?
PermaBase is warranted for a period of 30 years on interior applications and 10
years on exterior applications. Please see the following link for warranty details.
>
Back to Top
Technical Questions
Does PermaBase have a 1 hr and 2 hr fire rated assembly?
Yes, PermaBase achieves a 1-hour and 2-hour fire rating using approved assemblies
as witnessed by the Underwriters Laboratories and Warnock Hersey.
Click here to view these assemblies.
>
Back to Top
Does PermaBase have a flame and smoke spread rating?
Yes, PermaBase has a flame spread of 0 and a smoke spread of 0.
>
Back to Top
What is the insulating or thermal value of PermaBase?
1/2" PermaBase has an R/k value of .2/2.7 1/4" PermaBase has an R/k value of .1/2.7
>
Back to Top
I live in an area that has heavy winters. Is PermaBase acceptable
to use in freeze/thaw conditions?
Yes, PermaBase has been tested and passed 100 freeze/thaw cycles in accordance with
ASTM C666 (Procedure B).
>
Back to Top
|